< Go Back

Updates to Renewable Heat Incentive (RHI) for Biomass (Sept 2017)

[14/09/2017]

Following the Renewable Heat Incentive (RHI) consultation in 2016, changes to the RHI come into effect from September 20th 2017, some of which have implications for new biomass plant developments. The table below summarises the changes to biomass tariffs.

In a nutshell, tariffs for all sizes of biomass plant have been merged into a single, two-tier system. What does this mean for new biomass plant developments?

 

Given the drop in the tariff for Medium sized biomass plants, operators looking to make an application for a plant within the 200kW to 1,000kW bracket should act fast to submit a duly made RHI application to Ofgem before 20th September 2017.

 

Related articles

Biomass Boiler Environmental Permitting Guide

Non-domestic Renewable Heat Incentive (RHI) Updates (December 2016)

Air Quality Modelling for Biomass Plants

Waste Wood Biomass Boiler Opportunities

Blog

Have renewable energy technologies turned the corner?

[12/10/17] The rollout of renewable energy in the UK has been met with considerable criticism. Despite the legally mandated requirement to cut…

Case Study

A&E Thompson - Bespoke Permit Variation

A&E Thompson needed a bespoke Environmental permit to allow them to expand their open-air block composting facility to 60,000 tonnes per annum capacity. A&E Thompson successfully…

Featured Post

Current Situation Surrounding Site Fire Prevention Plan Guidance

Since the Environment Agency released the new Fire Prevention Guidance Version 3 back in July 2016 there have been a number of changes made, which have added to the complexity of...