Brief

Consultancy support was required by Kemp Waste Management (KWM) to prepare a town and country planning application to extend their existing Recycling Centre. The extension of the site included the following elements: forming of a level of made ground on the site using reclaimed inert materials to build up ground form; forming of a new entrance and concrete access road into the site; forming of an earth bund of c.2m height to visually screen the site; and planting of trees to visually screen the site. The application also required the revision of the applicable land use class for the site to cover additional waste management related activities.

The Solution

The client initiated pre-application engagement with a Calderdale Council Planning Officer. Following this meeting, WRM  prepared the core application, organised the production of required site plans and then managed the submission to the Council. During the process, WRM fully liaised with the client, council planning officer and their associated subcontractor. Following validation, WRM  addressed a number of planning issues highlighted by statutory consultees.

Data Request – To initiate the project, WRM organised a mobilisation meeting with the client to further discuss details of the project and what information would be required to complete the application. Following this meeting a data request sheet was sent to the client to complete.

Production of Application – WRM started production with the Planning Statement which involved assessing the development against applicable planning policy whilst also reviewing the proximity to any key sensitive/environmental receptors. Once the data request was received, WRM produced a comprehensive Design and Access Statement which provided the required details of the project.

Planning Drawings – WRM liaised with their selected CAD subcontractor who started production on the site layout and site location plans.

Submission & Further Action – The whole application was submitted via the planning portal to Calderdale Council. During the technical determination phase, the Council requested a number of additional deliverables which were outside the scope of the initial proposals. The deliverables ranged from a Phase 1 Ground Contamination Report to elevation drawings which required WRM to identify a subcontractor who could undertake a topographically survey. WRM addressed each of these issues without delay to enable the application to go to committee.

Outcome – The application went to committee, whereby KWM where granted planning permission. Following this successful outcome, WRM have continued to provide support to the client to address specific planning conditions, such as a detailed design of the new site access road.