The Brief

WRM were commissioned by Grindley Biogas Ltd to secure the environmental permit for the operation of a  biomethane to grid Anaerobic Digestion Plant at Grindley House Farm, Stafford. The site processes 46,000 tpa with a feedstock blend of agricultural slurry and whole crop maize. WRM delivered all aspects of the application and were also responsible for the project management and delivery of the entire process.

The Solution

We advised the client on the most appropriate environmental permit to support the intended site operations. After reviewing and analysing both current and future capacity provision, as well as targeted feedstocks, we identified several permitting options and recommended SR2012 No09.

Our expert consultants also provided strategic and tactical advice on appropriate options to enable the legal operation during the initial seeding and commissioning of the digester.

The Outcome

After agreeing to a tight deadline, we successfully submitted the permit application on time and to the high quality expected by both the client and the Environmental Agency.

The permit was successfully granted on the 31/08/2016.

We are proud  of our team’s focus on quality and this is demonstrated by our 100% permit approval success rate.

If you’d like more information about AD plant permitting, please contact us today.

Need Assurance on Your Next Steps?

If your organisation is in need of an environmental or sustainability solution, the consultants at WRM can provide that assurance. Contact us today to learn more or to schedule a free, no-obligation consultation.